WC131 JulyAugust 2023 - Magazine - Page 32
TOP100
88LAKE MANITOBA AND LAKE ST. MARTIN
97SPRINGBANK OFF-STREAM
OUTLET CHANNELS PROJECT$600 MILLION RESERVOIR$432 MILLION
2022 Rank: 88
Location: Interlake, Man.
Owner: Government of Manitoba
Contractor: Multiple (TBD)
Engineer: Hatch; KGS Group; Tetra
Tech
Environmental Services: Stantec;
North/South Consultants Inc.; WSP
Global Inc.; and Magellanicum
Ecological Services
Other Key Players: Dillon Consulting
(preliminary design and construction
inspection services)
Funding: Public
• Federal: $247.5 million
• Provincial: $292.5 million
Substantial Completion: 2025
In 2011, southern
Manitoba experienced
widespread flooding
and Lake Manitoba
experienced excessively
high inflows through
the Waterhen River,
Whitemud River, and the Portage Diversion. Construction of
the Lake Manitoba and Lake St. Martin Outlet Channels Project
(Outlet Channels Project) will enhance flood protection to the
surrounding area and help to strengthen Manitoba’s existing
network of flood mitigation infrastructure. The $600 million flood
protection Project consists of a 24.6 kilometre (km) long channel
from Lake Manitoba and a 23.6 km long channel from Lake St.
Martin. The Lake Manitoba outlet channel includes an inlet at
Lake Manitoba and outlet at Lake St. Martin, a new water control
structure with a bridge and three new bridge crossings over the
outlet channel. The Lake St. Martin outlet channel includes an
inlet at Lake St. Martin and outlet at Lake Winnipeg, a new water
control structure with a bridge, as well as the necessary Manitoba
Hydro infrastructure to power the control structure.
32
WATER C AN ADA • JULY/AUGUS T 2023
2022 Rank: 97
Location: Calgary, Alta.
Owner: Government of Alberta
Engineer: Stantec; Golder-a WSP company (environmental); Wood-a
WSP company (consulting)
Contractor: VINCI Construction (general contractor)
Environmental Services: Stantec
Other Key Players: Graham (bridges and concrete structures)
Legal: McLennan Ross (Counsel for the Government of Alberta); Osler
(advisor to the Government of Alberta)
Funding: Public
Substantial Completion: 2024
The Springbank Off-stream reservoir represents the
Government of Alberta’s solution to mitigate severe flooding
along the Elbow River, like what took place in June of 2013.
Current plans call for a dry reservoir with a capacity of 70.2
million cubic metres, with an outlet structure to safely release
the water back to the river when safe to do so. The reservoir
will be located approximately 15 kilometres west of the City of
Calgary. In October 2021 voluntary agreements were reached
with landowners to secure the 3,700 acres of land needed for
the project. The tendering process for construction has begun,
with tenders sent to pre-qualified bidders. Construction is
slated to begin in early 2022. Alberta Environment and Parks
will be responsible for the operation of the project once
construction is complete.
WAT E R C A N A D A . N E T