2025 Top 50 Water Projects Report - Report - Page 33
TOP 50 WATER PROJECTS 2025
WASTEWATER
26
G.E. Booth Water Resource
Recovery Facility • $130 million
2024 Rank: 24
Location: Mississauga, Ont.
Owner: Peel Region
Engineering Consultant: CIMA+
Other Key Players: CIMA+, RV Anderson
Substantial Completion: 2028
THE G.E. BOOTH (Lakeview) Water Resource Recovery Facility
(WRRF) is the largest wastewater treatment plant in the Region of
Peel. Originally commissioned in 1955, the facility has undergone
multiple expansions and now boasts a capacity of 518 million litres
per day (MLD). It serves the eastern portion of Peel and parts of York
Region, treating municipal wastewater from residential, commercial,
and industrial sources.
To support the construction of approximately 47,000 new housing
units, the plant is being expanded to increase its wastewater treatment
capacity. This expansion is part of Peel’s new capital works master
plan, set for completion in 2025, which assesses infrastructure needs
to meet growth projections under Bill 23.
One key project identi昀椀ed for early advancement is the investment
to boost capacity at the G.E. Booth WRRF by an additional 40 MLD. This
increase could accommodate between 28,000 and 47,000 new housing
units, depending on the development mix. •
DRINKING WATER
27
Curve Lake FN,
Water Project • $120 million
Location: Curve Lake, ON
Key Players: Colliers Project Management
Services; PMA Consultants
Substantial Completion: TBD
THE $120 million water supply and
distribution system project in Curve Lake
addresses quantity and quality concerns
regarding the community’s raw water
supply. Studies concluded that the groundwater is rife with quality issues and cannot
meet current water demands. Forecasted
growth in residential housing and in the
reserve population by the year 2040 also
makes it necessary to secure a stable and
cost-e昀昀ective water supply. •
WAT E R C A N A D A . N E T
WATER C AN ADA’S TOP 50 WATER PRO JEC T S