2026 Top 50 Water Projects Report - Report - Page 40
TOP 50 WATER PROJECTS 2026
DRINKING WATER
44
Newcastle Water Supply Plant
$50,000,000
2025 Rank: 41
Project Owner: Region of Durham
Location: Newcastle, Ont.
Project Consultant: R.V. Anderson & Associates Ltd.; Eramosa Engineering
Other Key Players: NAC Constructors Ltd.
Substantial Completion: TBD
THE NEWCASTLE Water Supply Plant and Port of Newcastle Sewage
Pumping Station involves the construction of a new water supply and
treatment facility with a rated capacity of 16,400m3/day (3.6 MIGD).
The new water supply plant will be a multi-level structure with
underground water storage facilities (raw water well, backwash
equalization tank and clearwells) and basement area, and the above
ground levels housing water treatment process equipment including
chemical, electrical, mechanical, HVAC, instrumentation and controls,
and administration facilities. The project also includes replacement of
the existing pumping station for the water supply plant.
The new sewage pumping station consists of an underground
wet well and an above ground control building with electrical and
mechanical control equipment. •
DRINKING WATER
45
Oneida Nation of the Thames
Water Supply System • $43,000,000
2025 Rank: 42
Project Owner: Oneida Nation of the Thames
Location: Southwold, Ont.
Project Management: Colliers Project Leaders
Substantial Completion: 2026
40
WATER C AN ADA’S TOP 50 WATER PRO JEC T S
CREDIT
THE ONEIA NATION of the Thames has been under a boil water
advisory since 2019. To resolve this, a $43 million project is underway
to connect the community to the Lake Huron Primary Water Supply
System and upgrade its distribution network. The project involves
constructing an 18-kilometer pipeline to link Oneida’s existing water
system to the Lake Huron supply near Mount Brydges. Additionally,
the on-reserve distribution system will be upgraded and expanded
to ensure reliable access to safe drinking water and improved fire
protection. •
WAT E R C A N A D A . N E T